Lekki-Epe road rehabilitation Phase 1 95% completed — LASG

The Lagos State Government on Thursday said that the first phase of the rehabilitation and upgrading of the six-lane Eti-Osa/Lekki-Epe Expressway was 95 per cent completed.

L-R: Chairman, Ibeju Lekki Local Council Development Area, Mr Abdullahi Oluwa, Special Adviser to Governor Babajide Sanwo-Olu on Works and Infrastructure, Mrs Aramide Adeyoye, Permanent Secretary Office of Infrastructure, Mr Olufemi Daramola, during inspection of ongoing road projects in the Lekki Epe axis on Thursday in Lagos.

The Special Adviser to Gov. Babajide Sanwo-Olu on Works and Infrastructure, Mrs Aramide Adeyoye, disclosed this during an inspection tour of projects on the Lekki/Epe axis.

“Phase one, which is a total of about 18.75km, is 95 per cent completed. Anybody coming from Epe Junction to Eleko would see the way the whole road is transformed.

“Hitherto, the hues and cries were much, there were gullies and ditches all over the whole road.

“This was a road done over 40 years ago without drains,” she said.

Adeyoye appealed to motorists to exercise patience and obey traffic signs around the construction zone.

She said this was necessary to ensure timely delivery of the second phase of the project.

The News Agency of Nigeria (NAN) reports that phase 1 of the project is 18.75km and spans from Eleko Junction to Epe-T-Junction,.

Phase 2 is 26.7km, spanning from Abraham Adesanya Roundabout to Eleko Junction.

She called for attitudinal change on the part of motorists and commuters to restore sanity to the road as construction works progress on sections of Eleko T Junction back to Abraham Adesanya.

She appealed to Lagos residents to support the contractors on the project for success of the second phase by obeying traffic rules, imbibing lane discipline and patience around construction zones.

Adeyoye said the government was concerned about the hardship caused by gridlock.

She said the Sanwo-Olu-led administration was determined to replicate the success of speedy construction achieved on Phase 1 in the second phase.

Adeyoye promised to give residents and stakeholders the best value in terms of traffic management plans for the project.

She advised the contractor to adopt methods that would reduce traffic impact on phase 2, which is located on a busier terrain, prone to gridlock.

She said the progress recorded on phase 1, was already taming perennial flooding on the axis.

The special adviser said that the old road constructed over 40 years ago had no drains or drainage outfalls.

” A road is as good as its drains,” Adeyoye said.

The Chairman on Infrastructure, Lekki Estates Residents Association, Mr Suleman Bello, pledged support of residents for timely delivery of the project.

He said the association had begun sensitisation of residents and other stakeholders on need for patience around the construction corridor.

A representative of Craneburg, contractors on the project, Mr Zakhia El Bashanuny, said preliminary construction had begun on the second phase of the project.

He said it would be delivered ahead of scheduled delivery date.

El Bashanuny appealed for cooperation from the stakeholders and motorists.

He said that the gridlock around Awoyaya was not created by the construction but impatience of motorists refusing to obey traffic rules.

JOIN OUR PULSE COMMUNITY!

Unblock notifications in browser settings.

Eyewitness? Submit your stories now via social or:

Email: eyewitness@pulse.ng

Recommended articles

Ayu returns from Europe today amid N122.4m scandal

Ayu returns from Europe today amid N122.4m scandal

Sowore confronts Shetimma over Tinubu's absence at peace accord event

Sowore confronts Shetimma over Tinubu's absence at peace accord event

Scandal in PDP as NWC members return 'mysterious' N122.4m to the party

Scandal in PDP as NWC members return 'mysterious' N122.4m to the party

DSS arrests pilgrim who absconded in Israel in 2019

DSS arrests pilgrim who absconded in Israel in 2019

Adeleke hails Supreme Court verdict, dedicates victory to God

Adeleke hails Supreme Court verdict, dedicates victory to God

FG, States can utilise $750m NG-CARES fund — World Bank

FG, States can utilise $750m NG-CARES fund — World Bank

Peace Accord with Jonathan contributed to peaceful elections – Buhari

Peace Accord with Jonathan contributed to peaceful elections – Buhari

DSS arrests pilgrim who absconded in Israel in 2019

DSS arrests pilgrim who absconded in Israel in 2019

35,000 registered for Project T-MAX Initiative in Lagos – FG

35,000 registered for Project T-MAX Initiative in Lagos – FG

Get our Top Stories delivered to your inbox

Welcome to the Pulse Community! We will now be sending you a daily newsletter on news, entertainment and more. Also join us across all of our other channels - we love to be connected!