Apapa Bridge to be closed for repairs, says Federal Controller of Works

The Federal Controller of Works, Lagos, Mr Adedamola Kuti told the News Agency of Nigeria (NAN) in Lagos on Sunday.

The Federal Controller of Works, Lagos, Mr Adedamola Kuti told the News Agency of Nigeria (NAN) in Lagos on Sunday.

He said that Julius Berger Plc. , the  contractor handling the project,  was ready to move to site.

The controller said that the ministry was working on effective traffic diversion alternatives that would ensure minimal stresses on users then.

ADVERTISEMENT

He explained that the bridge was still in use because of an earlier emergency repair work done by Julius Berger to stabilise it.

He said that Messrs Buildwell Nigeria Ltd., had completed permanent repairs on an extension of the bridge which was damaged by fire.

He said that when  Julius Berger returned to  site, it  would carry out permanent repairs on the  portion of the bridge awarded to it.

“The repair work will  be done on the bridge slab on the outbound Apapa carriageway.

“The situation we have found ourselves now is that for Julius Berger to start work, it means we have to divert traffic and we are still looking for the best alternatives.

ADVERTISEMENT

“We have all sorts of trucks; lorries on this Apapa road, and as a result of that,  we are having problems of diversion and that is what we are still looking at.

“We hope that very soon, we will be able to come up with the best solution on how to solve the traffic situation there.

“We are grateful to the Federal Government that has intervened by awarding the contract for the permanent repairs of the bridge to Julius Berger Construction Company.

“We will be coming up with solutions on traffic diversions in the next few days,’’ he told NAN.

Kuti said that meetings were already ongoing with stakeholders and traffic regulatory agencies on how best to tackle the problem and  ensure minimal stress for road users.

ADVERTISEMENT

He explained that some materials needed for the repairs of the bridge could not be sourced locally.

Hence, the contractor could not work on the bridge during its  earlier closure to traffic, he said  .

The controller said that adequate announcements would be made when the diversion of traffic would be made.

He  appealed to road users to comply with directives of law enforcement and traffic agencies then.

NAN reports that the Minister of Power, Works and Housing, Mr Babatunde Fashion,  on Aug. 5, 2016, inspected the dilapidated Apapa Bridge which was damaged by fire.

ADVERTISEMENT

The effect of the fire   exposed some of brudge’s steel layers and made it to cave.

Fashola after a meeting with relevant stakeholders on Aug. 7, 2016 ordered the immediate closure of the bridge.

Julius Berger Plc  moved to site the following day to begin emergency repair works.

An impact assessment of the bridge was thereafter carried out by Julius Berger which advised the Federal Government to embark on its permanent repairs.

This was despite the emergency work then.

ADVERTISEMENT

However, in February 2017, the Federal Government ordered the closure of  another extended portion of the bridge four four months for total rehabilitation.

The closed portion was about 700 metres long from the portion repaired by Julius Berger for four months.

However, due to paucity of funds,  the contractor abandoned site but the project was captured in 2017 budget leading to its award and subsequent permanent repair by Buildwell Nigeria Ltd.

NAN reports that the Apapa Bridge and the Marine Beach Bridge are jointly referred to as the Apapa-Ijora Bridge.Both bridges had been  damaged by fire at different times in the past.

Enhance Your Pulse News Experience!

Get rewards worth up to $20 when selected to participate in our exclusive focus group. Your input will help us to make informed decisions that align with your needs and preferences.

I've got feedback!

JOIN OUR PULSE COMMUNITY!

Unblock notifications in browser settings.
ADVERTISEMENT

Eyewitness? Submit your stories now via social or:

Email: eyewitness@pulse.ng

Recommended articles

Dana aircraft skids off Lagos Airport runway

Dana aircraft skids off Lagos Airport runway

Biden assures Zelensky of rapid arms support amid escalating Russia tensions

Biden assures Zelensky of rapid arms support amid escalating Russia tensions

NYSC praises Fintiri's approval of ₦10k monthly allowance for corps members

NYSC praises Fintiri's approval of ₦10k monthly allowance for corps members

Kano Govt invests over ₦68m in media equipment upgrade, trains 300 staff

Kano Govt invests over ₦68m in media equipment upgrade, trains 300 staff

No Nigerian is denied access, we aim for friendship between countries - CGCC

No Nigerian is denied access, we aim for friendship between countries - CGCC

Reno Omokri labels Abuja Chinese Supermarket 'racist', demands Wike's action

Reno Omokri labels Abuja Chinese Supermarket 'racist', demands Wike's action

1,500 Ogun residents receive free surgeries, 80k students get ₦50k each

1,500 Ogun residents receive free surgeries, 80k students get ₦50k each

NERC shifts Enugu electricity market oversight to State commission

NERC shifts Enugu electricity market oversight to State commission

Gov Diri & his deputy, Ewhrudjakpo cleared of certificate forgery allegations

Gov Diri & his deputy, Ewhrudjakpo cleared of certificate forgery allegations

ADVERTISEMENT
ADVERTISEMENT